Galpin Boulevard Is Open Again. Here's What Chanhassen's West Side Got for the Wait

  • October 29, 2026

"We know construction brought disruptions and took longer than anticipated." That line closed the City of Chanhassen's October 22 announcement that the Galpin Boulevard Improvement Project is officially complete. The rebuild took two full construction seasons and covered 2.1 miles, from West 78th Street to the northern city limits. The city had reported a cost of just over $17 million.

From behind the wheel, the obvious change is the roundabouts. The bigger change is on foot. The rebuilt Galpin is now a trail corridor as much as a road, and it was built to link up with paths that are only partly in place. Some of those links are close to finished. One has no date at all. Knowing which is which shapes how the corridor will work for anyone walking or biking it this winter and in the years ahead.

Why the finish line depended on Highway 41

Galpin's last step depended on a separate project. Final paving could not be scheduled until Highway 41 north of Highway 5 reopened. That stretch of 41 is part of the Carver County–led Highway 5 Improvements Project, and the city expected it to reopen October 5. Once 41 was carrying traffic again, the city scheduled Galpin's final paving for the MEA school break. Galpin closed from the north side of the West 78th Street roundabout to the south side of the Longacres roundabout starting Tuesday, October 13. Crews planned to mill and patch that day, pave Wednesday and Thursday, and finish striping by Saturday.

The project hub had listed construction as "Spring 2024 - Spring 2026." The final paving week ended up waiting on the reopening of a neighboring road. The local newsletter What's Chanhappenin' summed it up in its October 5 issue: "Highway 41 reopens just in time for Galpin Boulevard to close for paving."

The road also has a new owner. According to the project history, jurisdiction moved from Carver County to the City of Chanhassen, and the city handles routine and future maintenance now that construction is complete.

Four roundabouts, south to north

The city's completion notice lists four new roundabouts. From south to north, here is the order you'll meet them on the drive:

  1. West 78th Street, the southern anchor, a short distance from Lake Ann Park at 1456 W. 78th Street.
  2. Brinker Street
  3. Long Acres Drive
  4. Lake Lucy Road, where the trail layout changes.

Below the pavement, the project replaced and rehabilitated water and sewer lines, expanded sewer access, and improved stormwater management. It also added new curbs and drainage built for long-term durability. None of that work shows from the road.

Some cross-street names will sound familiar from other projects. The city's Highway 41 corridor page shows separate roundabouts planned where Lake Lucy Road and Longacres Drive meet Highway 41, now targeted for summer 2030. Galpin got its roundabouts at those cross streets first. The Highway 41 versions are still years away.

The trail splits at Lake Lucy Road

The Lake Lucy Road roundabout is where Galpin changes from a walking corridor into a placeholder. South of it, the project built new 10-foot-wide trails on both sides of the road. North of it, the city relocated a single trail to support a future connection toward Highway 7.

That future connection has no funding, construction date, or responsible agency attached to it in anything the city has published. The relocation is groundwork for a segment that does not exist yet. For now, the north end is a trail placed to meet a future one.

The southern half is ready to use now. With trails on both sides, people on either side of Galpin can walk or bike without crossing the road first. The clearest destination on the corridor is Sugarbush Park at 7220 Galpin Boulevard, which the city lists as having trail connections. At the southern end, the West 78th roundabout puts you a short distance from Lake Ann Park, which lists trails among its amenities.

The preserve trail filling the gap between Lake Ann and Lake Lucy

The forest and wetlands between Lake Ann and Lake Lucy are where Galpin's trail system starts to look like a network. The Lake Ann Park Preserve carries out what the city calls a fifty-year plan to protect that land, reached after extensive negotiations with Lennar. One of its stated goals is to continue trails around Lake Ann toward an eventual loop.

This year's construction targeted the northern segment, a paved 10-foot trail from the Greenwood Shores Park boardwalk to the Bluffs at Lake Lucy, extending toward Della Drive and Lucy Ridge Court. A new parking lot at Greenwood Shores was part of the same contract. The city received eight bids in January, ranging from about $783,000 to $1.09 million.

Here is where things stood late in the summer:

Preserve milestone Status reported by the city
Trail paving 2,800 feet paved as of an August 17 city video
Bridge abutments on Boardwalks B and C Concrete poured August 24
Greenwood Shores parking lot Grading still upcoming as of August 17
Opening Expected "this fall," per the August 19 city newsletter
Southern route to Boardwalk A near Paisley Path Paused by Council direction in March; existing natural trail kept

The city has announced a fall opening but not a specific date, and it said in August that it looked forward to holding a ribbon cutting. Before heading out, check the preserve project page for the current status. The city has asked people to stay off the boardwalks while fresh concrete cures.

The southern decision matters for winter. In its March work-session recap, the city said the Council supported pausing investment in the southern segment and keeping the existing natural trail, which will not be maintained in winter. Lake Ann and Lake Lucy will be linked through the preserve by both pavement and dirt, and the dirt portion is expected to stay unplowed.

What winter looks like on the new pavement

The city's trails page describes a 66-mile municipal system and says all city trails are cleared of snow using trucks, bobcats, tractors, plows and snow blowers. This is the first winter since construction began that the two new southern trails along Galpin are finished pavement and no longer part of a work zone.

Highway 5 work continues through autumn 2027

Galpin is finished, and so is the Highway 41 stretch north of Highway 5, but west-side construction is not over. Carver County's Highway 5 Improvements Project is widening Highway 5 from two lanes to four west of Highway 41 toward Victoria, adding pedestrian and trail connections, and building a roundabout at Highway 5 and Commercial Avenue. The county says Highway 41 south of Highway 5 to 82nd Street stayed closed through the 2026 construction season. In 2027, work moves to Highway 5 between Victoria and Chanhassen, with construction planned through autumn 2027. MnDOT's 2026 construction list also mentions a pedestrian bridge and new trails among the county's work.

This fall, Galpin's finish depended on Highway 41 reopening first, and the county's remaining Highway 5 work is scheduled through autumn 2027.

On the calendar, the city's Tree Lighting Ceremony is December 5 at 5 p.m. at City Center Park, with reindeer, bonfires, s'mores, carolers and Santa. The free Tour of Lights runs through Chanhassen neighborhoods December 5 to 31, from 5 to 9 p.m.

Curious how a rebuilt corridor like Galpin plays into home values on Chanhassen's west side? Our in-house appraisers follow these projects closely. Chestnut Realty is glad to walk you through what the new roundabouts, trails and upcoming connections mean for your street. Talk with a local Chestnut Realty expert.